Block bedding (about 3/8 in joints)
- Ratio
- 1 × 80 lb bag
- Water
- 2.5–3 qt
- Mixing
- 3–5 min, rest 5, remix
- Working time
- 1–1.5 h
- Cure
- 24 h before load
Full bed, not spot dabs; check level after every block.
Mixing guides
Mortar is cement and sand — no gravel. The same bag is mixed to different consistencies for bedding, laying and grout; the joint decides how wet it should be.
The bag or tube wins
By job
Full bed, not spot dabs; check level after every block.
It should hold a trowel ridge; back-butter each piece — spread mortar on its back — so no hollow spots remain.
Work it while the bed is still alive; strike flush and wipe haze as you go.
Temperature
40–90°F (5–32°C)
Rain
No rain or freezing for 24 hours. Cover fresh work.
Watch for
Crumbly joints
Likely cause: Mix too dry, or it dried too fast in sun and wind.
Fix: Mix to the right consistency; shade and mist the first day.
Hollow-sounding stone
Likely cause: Dry spots under the piece, or the mortar skinned over before setting.
Fix: Back-butter each piece (mortar on its back) and set it with a slight twist while the bed is alive.
Mortar haze on the faces
Likely cause: Wiping too late, after the film cured.
Fix: Wipe as you go with a damp sponge; never let a film dry on porous stone.